Irrigation Rehabilitation Program Project Construction August 1, 2007 to July 31, 2008

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 Table 2 - Project Construction
Rehabilitation Completed
(lengths in metres)
Irrigation District
Project #
ICW
MW
PS
Project Name
Project Approval Date
Construction Start Date
% Completed in 06/07
% Completed to July 31/08
Liners
Pipe
Earth
AID
2105
ICW
Lateral C10 Aetna Pipeline
2007 02
N/A
N/A
N/A
preliminary engineering
BRID
2078
MW
Lomond Lateral
2007 02
2007 10
100%
100%
560
3555
BRID
2091
ICW
Flow Measurement 2007
2007 02
2007 05
35%
100%
complete 3 of 8 sites
BRID
2122
ICW
Flow Measurement & Automation 2008
2008 02
2008 05
50%
50%
complete 2 of 4 sites
EID
2056
ICW
16 Springhill & 02-16 Springhill Pipeline
2006 02
2007 10
100%
100%
1569
20283
2118
EID
2129
ICW
EID Flow Measurement/Automation (2008)
2008 02
2008 04
25%
25%
complete 1 of 4 sites
LID
2102
ICW
Lateral K Water Measurement
2007 02
2008 05
100%
100%
flow meter on pipeline
LNID
1911
ICW
Keho/Barons Irrigation Project
2002 12
2008 03
100%
100%
flow meters on turnouts
LNID
1971
ICW
Automation Project (LNID)
2003 02
2003 03
20%
55%
two measurement sites
LNID
2142
ICW
On-Farm Pipeline Meters (Piyami)
2008 06
2008 03
100%
100%
flow meters on turnouts
MID
1983
ICW
Highline Pipeline
2004 02
2006 09
20%
65%
1821
MVID
2103
ICW
Highway 800 Water Measurement
2007 02
2008 05
100%
100%
flow meter on pipeline
RID
2066
ICW
Stirling #8 Pipeline
2006 02
2007 11
70%
70%
5621
SMRID
1862
ICW
North Lateral Gravel Armouring
2001 12
2002 10
9%
62%
1500
SMRID
1878
ICW
Bow Island Lateral 10B
2001 08
2001 11
15%
83%
5072
SMRID
2051
ICW
West Medicine Hat Lateral 6
2006 05
2007 11
7%
7%
1425
SMRID
2052
ICW
Yellow Lake Lateral 4
2006 02
2007 10
17%
17%
3317
SMRID
2109
ICW
Main Canal Lateral 4
2007 09
2007 11
35%
35%
3155
SMRID
2112
ICW
SMRID Flow Measurement Project
2007 11
2008 04
100%
100%
nine sites
SMRID
2113
MW
Lethbridge Lateral Headgates
2007 11
2008 02
100%
100%
overshot gates
TID
2076
ICW
Pipeline Drain Lines
2006 06
2006 04
8%
72%
456
TID
2085
ICW
Bountiful Coulee Pipeline
2007 02
2007 10
100%
100%
4320
TID
2086
ICW
North Fincastle East Canal
2007 02
2007 08
100%
100%
782
TID
2089
ICW
Water Measurement
2007 08
2008 04
100%
100%
update four sites
TID
2114
ICW
Lateral 6 Barnwell
2008 02
2008 04
20%
20%
1300
TID
2119
ICW
TID Flow Measurement (2008)
2008 02
2008 05
33%
33%
install 1 of 3 sites
UID
2067
ICW
Lateral A7 Pipeline
2006 02
2007 08
100%
100%
5634
UID
2096
ICW
Lateral D4 Return Flow Measurement
2007 02
2008 04
100%
100%
flow measurement site
UID
2130
ICW
UID Inflow Metering Stations
2008 02
2008 05
50%
50%
flow measurement site
WID
2069
ICW
Sublateral 81D2 Pipeline
2007 02
2007 10
100%
100%
12342
WID
2080
ICW
Springvale/Stahville
2006 08
2007 12
100%
100%
9148
WID
2131
ICW
WID Flow Measurement, Automation, SCADA
2008 02
2008 05
40%
40%
install 3 of 8 sites
TOTALS
2911
73894
7173
GRAND TOTAL
83,978
 
 
 
 
Share via AddThis.com
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by .
This information published to the web on July 13, 2009.
Last Reviewed/Revised on June 6, 2017.