Irrigation Rehabilitation Program Project Construction August 1, 2007 to July 31, 2008 | |
|
|
|
|
|
|
| Table 2 - Project Construction
 | Rehabilitation Completed
(lengths in metres) |
Irrigation District | Project # | ICW
MW
PS | Project Name | Project Approval Date | Construction Start Date | % Completed in 06/07 | % Completed to July 31/08 | Liners | Pipe | Earth |
AID | 2105 | ICW | Lateral C10 Aetna Pipeline | 2007 02 | N/A | N/A | N/A | preliminary engineering |
BRID | 2078 | MW | Lomond Lateral | 2007 02 | 2007 10 | 100% | 100% | 560 |  | 3555 |
BRID | 2091 | ICW | Flow Measurement 2007 | 2007 02 | 2007 05 | 35% | 100% | complete 3 of 8 sites |
BRID | 2122 | ICW | Flow Measurement & Automation 2008 | 2008 02 | 2008 05 | 50% | 50% | complete 2 of 4 sites |
EID | 2056 | ICW | 16 Springhill & 02-16 Springhill Pipeline | 2006 02 | 2007 10 | 100% | 100% | 1569 | 20283 | 2118 |
EID | 2129 | ICW | EID Flow Measurement/Automation (2008) | 2008 02 | 2008 04 | 25% | 25% | complete 1 of 4 sites |
LID | 2102 | ICW | Lateral K Water Measurement | 2007 02 | 2008 05 | 100% | 100% | flow meter on pipeline |
LNID | 1911 | ICW | Keho/Barons Irrigation Project | 2002 12 | 2008 03 | 100% | 100% | flow meters on turnouts |
LNID | 1971 | ICW | Automation Project (LNID) | 2003 02 | 2003 03 | 20% | 55% | two measurement sites |
LNID | 2142 | ICW | On-Farm Pipeline Meters (Piyami) | 2008 06 | 2008 03 | 100% | 100% | flow meters on turnouts |
MID | 1983 | ICW | Highline Pipeline | 2004 02 | 2006 09 | 20% | 65% |  | 1821 |  |
MVID | 2103 | ICW | Highway 800 Water Measurement | 2007 02 | 2008 05 | 100% | 100% | flow meter on pipeline |
RID | 2066 | ICW | Stirling #8 Pipeline | 2006 02 | 2007 11 | 70% | 70% |  | 5621 |  |
SMRID | 1862 | ICW | North Lateral Gravel Armouring | 2001 12 | 2002 10 | 9% | 62% |  |  | 1500 |
SMRID | 1878 | ICW | Bow Island Lateral 10B | 2001 08 | 2001 11 | 15% | 83% |  | 5072 |  |
SMRID | 2051 | ICW | West Medicine Hat Lateral 6 | 2006 05 | 2007 11 | 7% | 7% |  | 1425 |  |
SMRID | 2052 | ICW | Yellow Lake Lateral 4 | 2006 02 | 2007 10 | 17% | 17% |  | 3317 |  |
SMRID | 2109 | ICW | Main Canal Lateral 4 | 2007 09 | 2007 11 | 35% | 35% |  | 3155 |  |
SMRID | 2112 | ICW | SMRID Flow Measurement Project | 2007 11 | 2008 04 | 100% | 100% | nine sites |
SMRID | 2113 | MW | Lethbridge Lateral Headgates | 2007 11 | 2008 02 | 100% | 100% | overshot gates |
TID | 2076 | ICW | Pipeline Drain Lines | 2006 06 | 2006 04 | 8% | 72% |  | 456 |  |
TID | 2085 | ICW | Bountiful Coulee Pipeline | 2007 02 | 2007 10 | 100% | 100% |  | 4320 |  |
TID | 2086 | ICW | North Fincastle East Canal | 2007 02 | 2007 08 | 100% | 100% | 782 |  |  |
TID | 2089 | ICW | Water Measurement | 2007 08 | 2008 04 | 100% | 100% | update four sites |
TID | 2114 | ICW | Lateral 6 Barnwell | 2008 02 | 2008 04 | 20% | 20% |  | 1300 |  |
TID | 2119 | ICW | TID Flow Measurement (2008) | 2008 02 | 2008 05 | 33% | 33% | install 1 of 3 sites |
UID | 2067 | ICW | Lateral A7 Pipeline | 2006 02 | 2007 08 | 100% | 100% |  | 5634 |  |
UID | 2096 | ICW | Lateral D4 Return Flow Measurement | 2007 02 | 2008 04 | 100% | 100% | flow measurement site |
UID | 2130 | ICW | UID Inflow Metering Stations | 2008 02 | 2008 05 | 50% | 50% | flow measurement site |
WID | 2069 | ICW | Sublateral 81D2 Pipeline | 2007 02 | 2007 10 | 100% | 100% |  | 12342 |  |
WID | 2080 | ICW | Springvale/Stahville | 2006 08 | 2007 12 | 100% | 100% |  | 9148 |  |
WID | 2131 | ICW | WID Flow Measurement, Automation, SCADA | 2008 02 | 2008 05 | 40% | 40% | install 3 of 8 sites |
TOTALS | 2911 | 73894 | 7173 |
GRAND TOTAL |  | 83,978 |  |
|
|
|
|
|
|
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by .
This information published to the web on July 13, 2009.
Last Reviewed/Revised on June 6, 2017.
|
|