 During this reporting period the MID expended $497,217 of IRP cost shared funds on two projects in the ICW category. The one project with significant construction in 2007/2008 is listed below.




MID IRP Project Construction Summary
August 1, 2007 to July 31, 2008
Date
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project
Name
Project
Approved
Construction
Start
% Completed in 07/08
% Completed to July 31/08
Liners
Pipe
Earth
1983
ICW
Highline Pipeline
2004 02
2006 09
20%
65%
1821
 
 
 
 