Magrath Irrigation District (MID) | |
|
|
|
|
|
|
| During this reporting period the MID expended $497,217 of IRP cost shared funds on two projects in the ICW category. The one project with significant construction in 2007/2008 is listed below.MID IRP Project Construction Summary
August 1, 2007 to July 31, 2008
 | Date | Rehabilitation Completed
(metres) |
IRP # | ICW/
MW/
PS | Project
Name | Project
Approved | Construction
Start | % Completed in 07/08 | % Completed to July 31/08 | Liners | Pipe | Earth |
1983 | ICW | Highline Pipeline | 2004 02 | 2006 09 | 20% | 65% | 1821 |
|
|
|
|
|
|
For more information about the content of this document, contact Rebecca Fast.