Aetna Irrigation District (AID) - IRP 2017

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 During this reporting period the AID expended $80,435 of IRP cost shared funds on one project in the ICW
category, which involved pipeline installation.



AID IRP Project Construction Summary
August 1, 2016 to July 31, 2017
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
in 16/17
to July 31/17
Liners
Pipe
Earth
2322
ICW
C10 Pipeline
Enhancement
2016 02
2017 03
99
99
1,619

 
 
 
 
Share via AddThis.com
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by Rupal Mehta.
This information published to the web on May 30, 2018.