Raymond Irrigation District (RID) - IRP 2010 | |
|
|
|
|
|
|
| During this reporting period the RID expended $995,007 of IRP cost shared funds on five projects in the ICW category. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. Only one project with significant construction in 2009/2010 is listed below.
RID IRP Project Construction Summary
August 1, 2009 to July 31, 2010 | Date | % Completed | Rehabilitation Completed
(metres) |
IRP # | ICW/
MW/
PS | Project Name | Project
Approved | Construction
Start | in 09/10 | to July 31/10 | Liners | Pipe | Earth |
2155 | ICW | Welling Lateral 6 & 7 | 2009 02 | 2009 09 | 100% | 100% |  | 6725 |  |
TOTAL |  | 6725 |  |
|
|
|
|
|
|
For more information about the content of this document, contact Rebecca Fast.