Irrigation Rehabilitation Program Project Construction August 1, 2008 to July 31, 2009

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 Table 2 - Project Construction
Rehabilitation Completed
(lengths in metres)
Irrigation District
Project #
ICW
MW
PS
Project Name
Project Approval Date
Construction Start Date
% Completed in 08/09
% Completed to July 31/09
Liners
Pipe
Earth
AID
2105
ICW
C10 (Aetna) Pipeline
2008 06
2009 01
100%
100%
715
5678
AID
2141
ICW
Pipeline Upgrade
2008 06
2009 04
100%
100%
140
BRID
2102
MW
Lomond Lateral
2008 02
2008 10
100%
100%
2133
696
2167
BRID
2110
ICW
Lateral C3 (West Block)
2008 02
2008 11
100%
100%
640
BRID
2111
ICW
Lateral D-1, D-1-4 (West Block)
2008 02
2008 09
100%
100%
13603
BRID
2118
ICW
Lateral H-6-2 (West Block)
2008 02
2008 10
100%
100%
8810
BRID
*2122
MW
Flow Measurement/Automation 2008
2008 02
2008 05
65%
100%
4 sites installed
BRID
2136
ICW
Drain 110A (Hays Block)
2008 02
2008 09
100%
100%
500m spillway rehab
BRID
2149
ICW
Lateral M2 (West Block))
2008 09
2009 04
100%
100%
338
EID
*2129
ICW
EID Flow Measurement, Automation (2008)
2008 06
2009 03
50%
100%
5 sites installed
EID
2134
ICW
Kitsim Feeder Canal
2008 02
2008 11
100%
100%
8750
EID
2135
ICW
Kitsim Bypass Canal
2008 02
2008 08
100%
100%
2555
EID
*2145
ICW
Open Channel Flow Measurement
2008 06
2009 04
100%
100%
8 sites installed
LNID
2059
ICW
Laterals F6/F7
2007 02
2008 08
55%
55%
19290
MID
1983
ICW
Highline Pipeline
2004 02
2006 09
15%
80%
2099
MID
*2128
ICW
MID Inflow Metering Stations
2008 06
2008 11
100%
100%
2 sites installed
RID
2066
ICW
Stirling #8
2007 02
2007 11
30%
100%
2860
RID
2166
ICW
Sauder Reservoir Spillway Gate
2008 02
2008 08
100%
100%
cast-in-place structure
RID
*2146
ICW
RID Inflow Measurement
2008 06
2009 05
40%
40%
15 sites installed
RID
2156
ICW
Welling 5-1 Pipeline
2008 02
2009 03
100%
100%
1220
SMRID
1799
ICW
Bow Island Lateral 26
1998 06
2008 10
5%
5%
1605
SMRID
1862
MW
North Lateral Armouring
2001 12
2002 10
8%
70%
1370
SMRID
1878
ICW
Bow Island Lateral 10B
2001 08
2001 11
17%
6261
SMRID
2051
ICW
West Medicine Hat Lateral 6
2006 05
2007 11
32%
39%
7617
SMRID
2052
ICW
Yellow Lake Lateral 4
2006 02
2007 10
24%
41%
4934
SMRID
2109
ICW
Main Canal Lateral 4
2007 09
2007 11
20%
55%
2284
SMRID
2116
MW
Sauder Reservoir Spillway Gate
2008 02
2008 08
100%
100%
cast-in-place structure
SMRID
*2112
ICW
SMRD Flow Measurement Project
2007 11
2008 04
100%
100%
9 sites installed
SMRID
*2127
ICW
SMRID Open Channel Flow Measurement
2008 02
2009 04
65%
65%
6 sites installed
TID
1565
ICW
Lateral 3B Taber
2006 06
2008 08
100%
100%
128
TID
2114
ICW
Lateral 6 Barnwell
2008 02
2008 10
35%
55%
2410
TID
*2119
ICW
TID Flow Measurement (2008)
2008 02
2008 04
67%
100%
2 sites installed
TID
2125
ICW
Sauder Reservoir Spillway Gate
2008 02
2008 08
100%
100%
cast-in-place structure
UID
2093
ICW
Lateral D8
2007 02
2008 09
100%
100%
2872
UID
2094
ICW
Lateral A5
2007 02
2008 08
100%
100%
1556
UID
2115
ICW
Lateral B7, B7b
2008 02
2009 02
100%
100%
3183
UID
*2130
ICW
UID Inflow Metering Stations
2008 02
2009 05
50%
100%
1 site installed
UID
2158
ICW
Lateral D3, D3a
2009 02
2009 05
5%
5%
375
WID
2124
ICW
Secondary A Canal
2008 02
2008 09
100%
100%
601
8216
WID
*2131
ICW
WID Flow Measurement, Automation, SCADA
2008 06
2009 05
67%
100%
2 sites installed
WID
*2132
ICW
WID Return Flow Measurement
2008 06
2008 11
100%
100%
13 sites upgraded
TOTALS
2848
89200
23058
GRAND TOTAL
115,106
 
 
 
 
Share via AddThis.com
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by .
This information published to the web on March 5, 2010.
Last Reviewed/Revised on April 16, 2015.