Irrigation Rehabilitation Program Project Construction August 1, 2008 to July 31, 2009 | |
|
|
|
|
|
|
| Table 2 - Project Construction
 | Rehabilitation Completed
(lengths in metres) |
Irrigation District | Project # | ICW
MW
PS | Project Name | Project Approval Date | Construction Start Date | % Completed in 08/09 | % Completed to July 31/09 | Liners | Pipe | Earth |
AID | 2105 | ICW | C10 (Aetna) Pipeline | 2008 06 | 2009 01 | 100% | 100% | 715 | 5678 |  |
AID | 2141 | ICW | Pipeline Upgrade | 2008 06 | 2009 04 | 100% | 100% |  | 140 |  |
BRID | 2102 | MW | Lomond Lateral | 2008 02 | 2008 10 | 100% | 100% | 2133 | 696 | 2167 |
BRID | 2110 | ICW | Lateral C3 (West Block) | 2008 02 | 2008 11 | 100% | 100% |  | 640 |  |
BRID | 2111 | ICW | Lateral D-1, D-1-4 (West Block) | 2008 02 | 2008 09 | 100% | 100% |  | 13603 |  |
BRID | 2118 | ICW | Lateral H-6-2 (West Block) | 2008 02 | 2008 10 | 100% | 100% |  | 8810 |  |
BRID | *2122 | MW | Flow Measurement/Automation 2008 | 2008 02 | 2008 05 | 65% | 100% | 4 sites installed |
BRID | 2136 | ICW | Drain 110A (Hays Block) | 2008 02 | 2008 09 | 100% | 100% | 500m spillway rehab |
BRID | 2149 | ICW | Lateral M2 (West Block)) | 2008 09 | 2009 04 | 100% | 100% |  | 338 |  |
EID | *2129 | ICW | EID Flow Measurement, Automation (2008) | 2008 06 | 2009 03 | 50% | 100% | 5 sites installed |
EID | 2134 | ICW | Kitsim Feeder Canal | 2008 02 | 2008 11 | 100% | 100% |  |  | 8750 |
EID | 2135 | ICW | Kitsim Bypass Canal | 2008 02 | 2008 08 | 100% | 100% |  |  | 2555 |
EID | *2145 | ICW | Open Channel Flow Measurement | 2008 06 | 2009 04 | 100% | 100% | 8 sites installed |
LNID | 2059 | ICW | Laterals F6/F7 | 2007 02 | 2008 08 | 55% | 55% | 19290 |
MID | 1983 | ICW | Highline Pipeline | 2004 02 | 2006 09 | 15% | 80% |  | 2099 |  |
MID | *2128 | ICW | MID Inflow Metering Stations | 2008 06 | 2008 11 | 100% | 100% | 2 sites installed |
RID | 2066 | ICW | Stirling #8 | 2007 02 | 2007 11 | 30% | 100% |  | 2860 |  |
RID | 2166 | ICW | Sauder Reservoir Spillway Gate | 2008 02 | 2008 08 | 100% | 100% | cast-in-place structure |
RID | *2146 | ICW | RID Inflow Measurement | 2008 06 | 2009 05 | 40% | 40% | 15 sites installed |
RID | 2156 | ICW | Welling 5-1 Pipeline | 2008 02 | 2009 03 | 100% | 100% |  | 1220 |  |
SMRID | 1799 | ICW | Bow Island Lateral 26 | 1998 06 | 2008 10 | 5% | 5% |  | 1605 |  |
SMRID | 1862 | MW | North Lateral Armouring | 2001 12 | 2002 10 | 8% | 70% |  |  | 1370 |
SMRID | 1878 | ICW | Bow Island Lateral 10B | 2001 08 | 2001 11 | 17% |  |  | 6261 |  |
SMRID | 2051 | ICW | West Medicine Hat Lateral 6 | 2006 05 | 2007 11 | 32% | 39% |  | 7617 |  |
SMRID | 2052 | ICW | Yellow Lake Lateral 4 | 2006 02 | 2007 10 | 24% | 41% |  | 4934 |  |
SMRID | 2109 | ICW | Main Canal Lateral 4 | 2007 09 | 2007 11 | 20% | 55% |  | 2284 |  |
SMRID | 2116 | MW | Sauder Reservoir Spillway Gate | 2008 02 | 2008 08 | 100% | 100% | cast-in-place structure |
SMRID | *2112 | ICW | SMRD Flow Measurement Project | 2007 11 | 2008 04 | 100% | 100% | 9 sites installed |
SMRID | *2127 | ICW | SMRID Open Channel Flow Measurement | 2008 02 | 2009 04 | 65% | 65% | 6 sites installed |
TID | 1565 | ICW | Lateral 3B Taber | 2006 06 | 2008 08 | 100% | 100% |  | 128 |  |
TID | 2114 | ICW | Lateral 6 Barnwell | 2008 02 | 2008 10 | 35% | 55% |  | 2410 |  |
TID | *2119 | ICW | TID Flow Measurement (2008) | 2008 02 | 2008 04 | 67% | 100% | 2 sites installed |
TID | 2125 | ICW | Sauder Reservoir Spillway Gate | 2008 02 | 2008 08 | 100% | 100% | cast-in-place structure |
UID | 2093 | ICW | Lateral D8 | 2007 02 | 2008 09 | 100% | 100% |  | 2872 |  |
UID | 2094 | ICW | Lateral A5 | 2007 02 | 2008 08 | 100% | 100% |  | 1556 |  |
UID | 2115 | ICW | Lateral B7, B7b | 2008 02 | 2009 02 | 100% | 100% |  | 3183 |  |
UID | *2130 | ICW | UID Inflow Metering Stations | 2008 02 | 2009 05 | 50% | 100% | 1 site installed |
UID | 2158 | ICW | Lateral D3, D3a | 2009 02 | 2009 05 | 5% | 5% |  | 375 |  |
WID | 2124 | ICW | Secondary A Canal | 2008 02 | 2008 09 | 100% | 100% |  | 601 | 8216 |
WID | *2131 | ICW | WID Flow Measurement, Automation, SCADA | 2008 06 | 2009 05 | 67% | 100% | 2 sites installed |
WID | *2132 | ICW | WID Return Flow Measurement | 2008 06 | 2008 11 | 100% | 100% | 13 sites upgraded |
TOTALS | 2848 | 89200 | 23058 |
GRAND TOTAL | 115,106 |
|
|
|
|
|
|
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by .
This information published to the web on March 5, 2010.
Last Reviewed/Revised on April 16, 2015.
|
|