Lethbridge Northern Irrigation District (LNID) - IRP 2010

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 During this reporting period the LNID expended $4,251,030 of cost shared funds on four projects in the ICW category. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. Those projects with significant construction in 2009/2010 are listed below.



LNID IRP Project Construction Summary
August 1, 2009 to July 31, 2010
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
% Completed
in 09/10
% Completed
to July 31/10
Liners
Pipe
Earth
2059
ICW
Lateral F6 & F7 Phase 2
2007 02
2009 09
45%
100%
14790
2150
ICW
Real-Time Return Flow Upgrades
2008 06
2010 03
100%
100%
5 sites with SCADA links
TOTAL
14790
 
 
 
 
Share via AddThis.com
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by .
This information published to the web on January 17, 2011.
Last Reviewed/Revised on December 6, 2017.