Lethbridge Northern Irrigation District (LNID) - IRP 2010 | |
|
|
|
|
|
|
| During this reporting period the LNID expended $4,251,030 of cost shared funds on four projects in the ICW category. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. Those projects with significant construction in 2009/2010 are listed below.
LNID IRP Project Construction Summary
August 1, 2009 to July 31, 2010 | Date | % Completed | Rehabilitation Completed
(metres) |
IRP # | ICW/
MW/
PS | Project Name | Project
Approved | Construction
Start | % Completed
in 09/10 | % Completed
to July 31/10 | Liners | Pipe | Earth |
2059 | ICW | Lateral F6 & F7 Phase 2 | 2007 02 | 2009 09 | 45% | 100% |  | 14790 |  |
2150 | ICW | Real-Time Return Flow Upgrades | 2008 06 | 2010 03 | 100% | 100% | 5 sites with SCADA links |
TOTAL |  | 14790 |  |
|
|
|
|
|
|
For more information about the content of this document, contact Rebecca Fast.