Irrigation Rehabilitation Program Project Construction August 1, 2016 to July 31, 2017

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 Table 2 - Project Construction

Rehabilitation Completed
(lengths in metres)
Irrigation Distrct
Project #
ICW
MW
Project Name
Project Approval Date
Construction Start Date
% Completed in 16/17
% Completed to July 31/17
Liners
Pipe
Earth
AID
2322
ICW
C10 Pipeline Enhancement
2016 02
2017 03
100
100
1,619
BRID
2319
ICW
Lateral B
(West Block)
2016 02
2016 04
39
42
6,480
EID
2327
ICW
11B Springhill
2016 02
2016 11
99
100
18,253
LNID
2302
ICW
Lateral H9
2015 02
2016 10
96
100
18,971
RID
2321
ICW
Welling Lateral #5 - Phase 5
2016 02
2016 11
99
100
4,185
SMRID
2198
ICW
South Grassy Main Lateral
2010 02
2016 01
41
53
11,348
TID
2239
ICW
Lateral E-3 Big Bend Pipeline
2012 03
2016 11
91
97
895
TID
2323
ICW
Lat 7 East Horsefly & Lat 20 Taber Structure Replacements
2016 02
2016 11
85
86
4 Structures removed and replaced
UID
2301
ICW
Lateral A1
2016 02
2016 10
96
98
1,554
UID
2320
ICW
Lateral A4.5
2016 04
2016 09
80
90
1,100
WID
2305
ICW
Standard Lateral 85N6
2016 02
2017 02
72
78
1,820
TOTAL
66,225 metres
 
 
 
 