 | Rehabilitation Completed
(lengths in metres) |
Irrigation District | Project # | ICW
MW
PS | Project Name | Project Approval Date | Construction Start Date | % Completed in 09/10 | % Completed to July 31/10 | Liners | Pipe | Earth |
AID | 2184 | PS | AID Comprehensive Planning Study | 2009 08 | 2009 08 | 100% | 100% | planning study |
BRID | 2123 | ICW | Lateral H (West Block) Seepage Control | 2008 02 | 2009 10 | 100% | 100% | 775 |  |  |
BRID | 2139 | ICW | Laterals R-3, R-4, r_8 (Hays Block) | 2009 02 | 2009 09 | 100% | 100% |  | 15600 |  |
BRID | 2143 | ICW | Laterals C-7 & C-6 (Hays Block) | 2009 02 | 2010 01 | 100% | 100% |  | 7347 |  |
BRID | 2144 | ICW | Lomond Lateral km 28.4 to km 32.1 | 2009 02 | 2009 11 | 100% | 100% | 1044 |  | 816 |
BRID | 2165 | ICW | Laterals R-6 & R-7 (Hays Block) | 2009 02 | 2009 11 | 100% | 100% |  | 4252 |  |
BRID | 2166 | ICW | Laterals C-8-4 (Hays Block) | 2009 02 | 2010 03 | 100% | 100% |  | 3518 |  |
BRID | 2167 | ICW | Structure Automation & Upgrades 2009 | 2009 02 | 2009 03 | 100% | 100% | 11 sites modified |
BRID | 2185 | ICW | Drain H-5 (Vauxhall Block) | 2010 03 | 2010 03 | 100% | 100% |  | 2131 |  |
BRID | 2187 | ICW | Lost Lake Pumphouse Screens | 2009 09 | 2010 03 | 100% | 100% | replace trash screens |
BRID | 2189 | ICW | Drain G (Vauxhall Block) | 2010 02 | 2009 12 | 100% | 100% |  | 240 |  |
BRID | 2197 | ICW | Main Canal Expanse Coulee Wasteway | 2010 02 | 2010 05 | 100% | 100% |  | 152 |  |
BRID | 2210 | ICW | Structure Automation & Flow Measurement | 2010 04 | 2010 06 | 100% | 100% | 12 sites automated |
BRID | 2211 | ICW | Reservoir H Main Dam Erosion Protection | 2010 05 | 2010 07 | 100% | 100% | rip-rap erosion control |
EID | 2172 | ICW | F Springhill | 2009 04 | 2009 12 | 100% | 100% |  | 25307 |  |
EID | 2174 | MW | North Bantry Canal Reach 1 | 2009 02 | 2009 10 | 100% | 100% | 1500 |  | 4448 |
LID | 2181 | PS | Comprehensive Planning Study | 2009 06 | 2009 08 | 100% | 100% | planning study |
LNID | 2059 | ICW | Lateral F6 & F7 Phase 2 | 2007 02 | 2009 09 | 45% | 100% |  | 14790 |  |
LNID | 2150 | ICW | Real-Time Return Flow Upgrades | 2008 06 | 2010 03 | 100% | 100% | 5 sites with SCADA link |
MID | 1983 | ICW | Highline Pipeline Phase 4 | 2004 02 | 2009 10 | 20% | 100% |  | 1408 |  |
MID | 2204 | ICW | Automated Screening 2010 | 2010 02 | 2010 04 | 100% | 100% | install 7 automated screens |
MVID | 2183 | PS | MVID Comprehensive Planning Study | 2009 08 | 2009 08 | 100% | 100% | planning study |
RID | 2155 | ICW | Welling 6 & 7 Pipeline | 2009 02 | 2009 09 | 100% | 100% |  | 6725 |  |
SMRID | 1799 | ICW | Bow Island Lateral 26 Concrete | 1998 06 | 2008 10 | 27% | 32% |  | 9625 |  |
SMRID | 1862 | ICW | North Lateral Gravel Armouring | 2001 12 | 2002 10 | 9% | 79% |  |  | 1505 |
SMRID | 1868 | ICW | South Medicine Hat Laterals 18, 19 & M | 2001 08 | 2010 04 | 100% | 100% |  | 500 |  |
SMRID | 2051 | ICW | West Medicine Hat Lateral 6 | 2006 05 | 2007 11 | 61% | 100% |  | 15050 |  |
SMRID | 2052 | ICW | Yellow lake Lateral 4 | 2006 02 | 2007 10 | 30% | 71% |  | 10254 |  |
SMRID | 2109 | ICW | Main Canal Lateral 4 | 2007 09 | 2007 11 | 45% | 100% |  | 4505 |  |
SMRID | 2127 | ICW | SMRID Open Channel Flow Measurement | 2008 02 | 2010 05 | 35% | 100% | 3 flow measurement sites |
SMRID | 2147 | ICW | Bow Island Lateral 10H-1 | 2009 02 | 2009 10 | 100% | 100% |  | 5219 |  |
SMRID | 2151 | ICW | Coaldale Sublaterals | 2009 02 | 2010 03 | 35% | 35% |  | 739 |  |
SMRID | 2152 | MW | Northeast Resevoir Inlet Gate | 2009 02 | 2010 02 | 100% | 100% | automated overshot gate |
SMRID | 2179 | PS | Murray Reservoir - Dam Safety Review | 2009 06 | 2009 09 | 100% | 100% |  |
SMRID | 2180 | PS | Chin Reservoir Flood Handling Study | 2009 06 | 2009 09 | 100% | 100% |  |
SMRID | 2192 | ICW | SMRID Aquatic Weed & Algae Control | 2009 11 | 2010 01 | 60% | 60% | 3 of 5 sites installed |
SMRID | 2208 | ICW | SCADA Infrastructure Upgrades | 2010 04 | 2010 05 | 50% | 50% | program upgrades |
TID | 2114 | ICW | Lateral 6 Barnwell (Phase 1) | 2008 02 | 2008 04 | 45% | 100% |  | 2966 |  |
TID | 2170 | ICW | Screens for Pipelines | 2010 02 | 2010 05 | 100% | 100% | install two trash screens |
TID | 2171 | ICW | Lateral 20-B2 Taber Pipeline | 2009 02 | 2010 04 | 100% | 100% |  | 146 |  |
TID | 2193 | ICW | South East Big Bend Pipeline | 2010 02 | 2010 02 | 100% | 100% |  | 1302 |  |
UID | 2092 | ICW | Lateral A1c | 2007 02 | 2009 08 | 100% | 100% |  | 2671 |  |
UID | 2130 | ICW | UID Inflow Metering Stations | 2008 02 | 2010 06 | 50% | 100% | 2 flow meters |
UID | 2159 | ICW | Lateral B4 | 2009 02 | 2009 11 | 100% | 100% |  | 1673 |  |
UID | 2161 | ICW | Lateral D | 2009 02 | 2010 03 | 17% | 17% |  |  | 851 |
UID | 2163 | ICW | Lateral Da | 2009 02 | 2010 05 | 100% | 100% |  | 1356 |  |
WID | 2157 | ICW | Secondary A Canal | 2009 02 | 2009 08 | 100% | 100% |  |  | 11250 |
TOTALS | 3319 | 137476 | 11870 |
GRAND TOTAL | 159665 |