 During this reporting period the UID expended $802,940 of IRP cost shared funds on seven projects. MW expenditures total $485 and ICW expenditures total $802,455. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. Those projects with significant construction in 2006/2007 are listed below.
.










Project #2095, Lateral D
Return Flow Measurement.
Precast structure with datalogger recording station.
.
UID IRP Project Construction Summary
August 1, 2006 to July 31, 2007
 
Date
Rehabilitation Completed
IRP #
 
ICW
MW
PS
Project
Name
Project Approved
Construction
Start
% Completed in 06/07
% Completed to July 31/07
Liners (metres)
Pipe
(metres)
 
Earth
(metres)
 
1963
ICW
Lateral B13
2003 02
2007 03
100%
100%
4465
1964
ICW
Lateral A4b
2003 02
2006 10
100%
100%
1315
2000
ICW
Lateral F
2004 02
2006 09
15%
100%
1063
*2095
ICW
Lateral D Return Flow Measurement
2007 02
2007 05
100%
100%
flow measurement station
5780
1063
 
 
 
 
For more information about the content of this document, contact Don Gross.
This document is maintained by Bob Winter.
This information published to the web on June 17, 2005.
Last Reviewed/Revised on February 8, 2008.