United Irrigation District (UID) | |
| |
|
|
| |
|
|
| | During this reporting period the UID expended $802,940 of IRP cost shared funds on seven projects. MW expenditures total $485 and ICW expenditures total $802,455. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. Those projects with significant construction in 2006/2007 are listed below.
.
 |
Project #2095, Lateral D
Return Flow Measurement.
Precast structure with datalogger recording station.
|  |
.
UID IRP Project Construction Summary
August 1, 2006 to July 31, 2007
| Date | Rehabilitation Completed |
IRP #
| ICW
MW
PS | Project
Name | Project Approved | Construction
Start | % Completed in 06/07 | % Completed to July 31/07 | Liners (metres) | Pipe
(metres)
| Earth
(metres)
|
| 1963 | ICW | Lateral B13 | 2003 02 | 2007 03 | 100% | 100% |  | 4465 |  |
| 1964 | ICW | Lateral A4b | 2003 02 | 2006 10 | 100% | 100% |  | 1315 |  |
| 2000 | ICW | Lateral F | 2004 02 | 2006 09 | 15% | 100% |  |  | 1063 |
| *2095 | ICW | Lateral D Return Flow Measurement | 2007 02 | 2007 05 | 100% | 100% | flow measurement station |
 |  |  |  |  |  |  |  | 5780 | 1063 |
|
|
| |
|
|
| |
For more information about the content of this document, contact Don Gross.
This document is maintained by Bob Winter.
This information published to the web on June 17, 2005.
Last Reviewed/Revised on February 8, 2008.
|
|