St. Mary River Irrigation District (SMRID) | |
| |
|
|
| |
|
|
| | During this reporting period the SMRID expended $7,760,449 of IRP cost shared funds on 14 projects. MW expenditures total $1,218,673 and ICW expenditures total $6,541,776. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. Those projects with significant construction in 2006/2007 are listed below.
.
 |  |
Project #1761, Northeast Lateral.
Before rehabilitation. | Project #1761, Northeast Lateral.
After rehabilitation. |
SMRID IRP Project Construction Summary
August 1, 2006 to July 31, 2007
| Date | Rehabilitation Completed |
IRP #
| ICW
MW
PS | Project
Name
| Project Approved | Construction
Start
| % Completed
in 06/07 | % Completed to July 31/07 | Liners (metres) | Pipe
(metres)
| Earth
(metres)
|
| 1761 | MW | Northeast Lateral | 1997 02 | 2006 10 | 100% | 100% |  | 987 | 1245 |
| 1862 | MW &
ICW | North Lateral Gravel Armouring | 2001 12 | 2002 10 | 10% | 53% |  |  | 1627 |
| 1866 | ICW | Bow Island Laterals 28, 28C, 30 | 2002 05 | 2003 02 | 19% | 100% |  | 7539 |  |
| 1878 | ICW | Lateral 10B | 2001 08 | 2001 11 | 8% | 73% |  | 2653 |  |
| 1991 | ICW | Yellow Lake Lateral 5 | 2004 02 | 2004 10 | 29% | 100% |  | 2526 |  |
| 1992 | ICW | S Medicine Hat Lat 2 | 2004 02 | 2005 03 | 50% | 100% |  | 7391 |  |
| 2023 | ICW | Whoop-Up Lateral | 2005 02 | 2006 10 | 25% | 25% |  | 4032 |  |
| 2049 | ICW | Pipeline Turnout Flow Monitoring | 2005 11 | 2006 05 | 60% | 100% | install 120 gauges |
| 2050 | ICW | S Medicine Hat Lat 10 | 2006 02 | 2007 03 | 100% | 100% |  | 3176 |  |
 |  |  |  |  |  |  |  | 28304 | 2872 |
|
|
| |
|
|
| |
For more information about the content of this document, contact Don Gross.
This document is maintained by Bob Winter.
This information published to the web on June 17, 2005.
Last Reviewed/Revised on February 8, 2008.
|
|