Ross Creek Irrigation District (RCID)

 
 
Subscribe to our free E-Newsletter, "RTW This Week"Sign up for our
E-Newsletter
 
 
 
 During this reporting period, the RCID completed construction of one project in the ICW category. This project is listed below.
.
Project #2013, RCID Closed Pipeline System.
Typical gate valve controlling flow to farm
Project #2013, RCID Closed Pipeline System.
Typical farm turnout riser with butterfly

RCID IRP Project Construction Summary
August 1, 2006 to July 31, 2007
Date
Rehabilitation Completed
IRP #
ICW
MW
PS
Project
Name
Project Approved
Construction
Start
% Completed in 06/07
% Completed to July 31/07
Liners (metres)
Pipe
(metres)
Earth
(metres)
*2013
ICW
RCID Closed Pipeline
2004 02
2006 02
30%
95%
5200
 
 
 
 
For more information about the content of this document, contact Don Gross.
This document is maintained by Bob Winter.
This information published to the web on June 17, 2005.
Last Reviewed/Revised on February 8, 2008.