Raymond Irrigation District (RID) | |
| |
|
|
| |
|
|
| | During this reporting period the RID expended $897,790 of IRP cost shared funds on three projects in the ICW category. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. One project with significant construction in 2006/2007 is listed below.
.
 |  |  |
Project #2060, Stirling #4.
Pipeline inlet structure. |  | Project #2060, Stirling #4.
Typical farm turnout riser to farmer pumping station. |
RID IRP Project Construction Summary
August 1, 2006 to July 31, 2007
| Date | Rehabilitation Completed |
IRP #
| ICW
MW
PS | Project
Name
| Project Approved | Construction
Start
| % Completed in 06/07 | % Completed to July 31/07 | Liners (metres) | Pipe
(metres)
| Earth
(metres)
|
| *2060 | ICW | Stirling #4 | 2006 02 | 2006 10 | 95% | 95% |  | 5859 |  |
|
|
| |
|
|
| |
For more information about the content of this document, contact Don Gross.