Lethbridge Northern Irrigation District (LNID)

 
 
Subscribe to our free E-Newsletter, "RTW This Week"Sign up for our
E-Newsletter
 
 
 
 During this reporting period the LNID expended $4,859,512 of cost shared funds on 10 projects in the ICW and PS category. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. Those projects with significant construction in 2006/2007 are listed below.
.
Project #1972, Lateral C12 Pipeline.
Pipeline screening chamber.
Project #2041, Lat 61C South Park Lake. Bituminous liner installed on concrete lining to eliminate seepage problems.

LNID IRP Project Construction Summary
August 1, 2006 to July 31, 2007
  
Date
Rehabilitation Completed
IRP #
 
ICW
MW
PS
Project
Name
 
Project Approved
Construction
Start
 
% Completed
in 06/07
% Completed
to July 31/07
Liners (metres)
Pipe
(metres)
 
Earth
(metres)
 
1970
PS
LNID Air Photos (2003)
2003 02
2007 07
100%
100%
update aerial photography
1972
ICW
Lateral C12 Pipeline
2003 02
2006 09
100%
100%
15505
2041
ICW
Lateral 61C South Park Lake
2005 03
2005 11
50%
100%
400
 
 
 
 
For more information about the content of this document, contact Don Gross.
This document is maintained by Bob Winter.
This information published to the web on June 20, 2005.
Last Reviewed/Revised on February 8, 2008.