Lethbridge Northern Irrigation District (LNID) | |
| |
|
|
| |
|
|
| | During this reporting period the LNID expended $4,859,512 of cost shared funds on 10 projects in the ICW and PS category. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. Those projects with significant construction in 2006/2007 are listed below.
.
 |  |
Project #1972, Lateral C12 Pipeline.
Pipeline screening chamber. | Project #2041, Lat 61C South Park Lake. Bituminous liner installed on concrete lining to eliminate seepage problems. |
LNID IRP Project Construction Summary
August 1, 2006 to July 31, 2007
| Date | Rehabilitation Completed |
IRP #
| ICW
MW
PS | Project
Name
| Project Approved | Construction
Start
| % Completed
in 06/07 | % Completed
to July 31/07 | Liners (metres) | Pipe
(metres)
| Earth
(metres)
|
| 1970 | PS | LNID Air Photos (2003) | 2003 02 | 2007 07 | 100% | 100% | update aerial photography |
| 1972 | ICW | Lateral C12 Pipeline | 2003 02 | 2006 09 | 100% | 100% | 15505 |  |  |
| 2041 | ICW | Lateral 61C South Park Lake | 2005 03 | 2005 11 | 50% | 100% | 400 |  |  |
|
|
| |
|
|
| |
For more information about the content of this document, contact Don Gross.
This document is maintained by Bob Winter.
This information published to the web on June 20, 2005.
Last Reviewed/Revised on February 8, 2008.
|
|