Leavitt Irrigation District (LID) | |
| |
|
|
| |
|
|
| | During this reporting period, the LID expended $65,160 of cost shared funds on five projects in the ICW category. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects and costs associated with one previously completed project. Those projects with significant construction in 2006/2007 are listed below.
.
 |  |
Project #2072, Coulee Delivery.
Pipeline connection to existing Lateral K Phase 2 turnout riser. | Project #2072, Coulee Delivery.
Pipeline route through coulee with drain line outlet. |
LID IRP Project Construction Summary
August 1, 2006 to July 31, 2007
| | Date | Rehabilitation Completed |
IRP #
| ICW
MW
PS | Project
Name
| Project Approved | Construction
Start
| % Completed in 06/07 | % Completed to July 31/07 | Liners (metres) | Pipe
(metres)
| Earth
(metres)
|
| 2072 | ICW | Coulee Delivery | 2006 02 | 2007 01 | 100% | 100% |  | 1827 |  |
| 2081 | ICW | Hamlet of Leavitt Lateral | 2006 09 | 2006 12 | 100% | 1005 |  | 1840 |  |
 |  |  |  |  |  |  |  | 3667 |  |
|
|
| |
|
|
| |
For more information about the content of this document, contact Don Gross.
This document is maintained by Bob Winter.
This information published to the web on June 20, 2005.
Last Reviewed/Revised on February 8, 2008.
|
|