Eastern Irrigation District (EID) | |
| |
|
|
| |
|
|
| | During this reporting period the EID expended $5,750,996 of IRP cost shared funds on three projects in the ICW category. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. The one project with significant construction in 2006/2007 is listed below.
.
 |  |
Project #2057, Lateral G North Bantry.
Banks built level on membrane lined Lateral G to become the pipeline settling pond. | Project #2057, Lateral G North Bantry.
Pipeline inlet with self-cleaning trash screen. |
EID IRP Project Construction Summary
August 1, 2006 to July 31, 2007
| Date | Rehabilitation Completed |
IRP #
| ICW
MW
PS | Project
Name
| Project Approved | Construction
Start
| % Completed in 06/07 | % Completed to July 31/07 | Liners (metres) | Pipe
(metres)
| Earth
(metres)
|
| 2057 | ICW | G North Bantry | 2006 02 | 2006 10 | 100% | 100% |  | 19656 |  |
|
|
| |
|
|
| |
For more information about the content of this document, contact Don Gross.