Eastern Irrigation District (EID)

 
 
Subscribe to our free E-Newsletter, "RTW This Week"Sign up for our
E-Newsletter
 
 
 
 During this reporting period the EID expended $5,750,996 of IRP cost shared funds on three projects in the ICW category. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. The one project with significant construction in 2006/2007 is listed below.
.
Project #2057, Lateral G North Bantry.
Banks built level on membrane lined Lateral G to become the pipeline settling pond.
Project #2057, Lateral G North Bantry.
Pipeline inlet with self-cleaning trash screen.

EID IRP Project Construction Summary
August 1, 2006 to July 31, 2007
 
 
Date
Rehabilitation Completed
IRP #
 
ICW
MW
PS
Project
Name
 
Project Approved
Construction
Start
 
% Completed in 06/07
% Completed to July 31/07
Liners (metres)
Pipe
(metres)
 
Earth
(metres)
 
2057
ICW
G North Bantry
2006 02
2006 10
100%
100%
19656
 
 
 
 
For more information about the content of this document, contact Don Gross.
This document is maintained by Bob Winter.
This information published to the web on June 20, 2005.
Last Reviewed/Revised on February 8, 2008.