Bow River Irrigation District (BRID) | |
| |
|
|
| |
|
|
| | During this reporting period the BRID expended $4,719,028 of IRP cost shared funds on 13 projects. MW expenditures total $28,712 and ICW expenditures total $4,747,740. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. Those projects with significant construction in 2006/2007 are listed below.
.
BRID IRP Project Construction Summary
August 1, 2006 to July 31, 2007
| Date | Rehabilitation Completed |
IRP #
| ICW
MW
PS | Project
Name
| Project Approved | Construction
Start
| % Completed in 06/07 | % Completed to July 31/07 | Liners (metres) | Pipe
(metres)
| Earth
(metres)
|
| *2026 | ICW | Laterals C1,C2,C3 Hays | 2006 02 | 2006 11 | 100% | 100% |  | 18012 |  |
| 2044 | ICW | Lomond Lateral | 2006 02 | 2006 10 | 100% | 100% |  |  | 3502 |
| *2091 | ICW | Flow Measurement 2007 | 2007 02 | 2007 05 | 65% | 65% | complete 5 of 8 sites |
|
|
| |
|
|
| |
For more information about the content of this document, contact Don Gross.
This document is maintained by Bob Winter.
This information published to the web on June 17, 2005.
Last Reviewed/Revised on February 8, 2008.
|
|