 During this reporting period the BRID expended $4,719,028 of IRP cost shared funds on 13 projects. MW expenditures total $28,712 and ICW expenditures total $4,747,740. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. Those projects with significant construction in 2006/2007 are listed below.
.
Project #2091, Flow Measurement 2007.
Gate position on large structures controlled by radio control from BRID office.
BRID IRP Project Construction Summary
August 1, 2006 to July 31, 2007
  
Date
Rehabilitation Completed
IRP #
 
ICW
MW
PS
Project
Name
 
Project Approved
Construction
Start
 
% Completed in 06/07
% Completed to July 31/07
Liners (metres)
Pipe
(metres)
 
Earth
(metres)
 
*2026
ICW
Laterals C1,C2,C3 Hays
2006 02
2006 11
100%
100%
18012
2044
ICW
Lomond Lateral
2006 02
2006 10
100%
100%
3502
*2091
ICW
Flow Measurement 2007
2007 02
2007 05
65%
65%
complete 5 of 8 sites
 
 
 
 
For more information about the content of this document, contact Don Gross.
This document is maintained by Bob Winter.
This information published to the web on June 17, 2005.
Last Reviewed/Revised on February 8, 2008.