Irrigation Rehabilitation Program Project Construction August 1, 2013 to July 31, 2014

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 Table 2 - Project Construction
Rehabilitation Completed
(lengths in metres)
Irrigation District
Project #
ICW
MW
PS
Project Name
Project Approval Date
Construction Start Date
% Completed in 13/14
% Completed to July 31/14
Liners
Pipe
Earth
BRID
2259
ICW
Lateral C
(West Block)
2013 02
2013 10
100%
100%
16846
EID
2173
ICW
Antelope Creek
2009 02
2013 10
100%
100%
3518
1550
EID
*2226
PS
Irrigation Water Quality Assessment
2012 02
2012 06
20%
60%
90 sites sampled
EID
2274
ICW
AH North Bantry
2013 02
2013 11
100%
100%
9356
RID
2262
ICW
Welling Lateral #5 Phase 2
2013 02
2013 12
100%
100%
1366
SMRID
2117
ICW
West Medicine Hat Lateral 16
2010 03
2013 11
100%
100%
5434
SMRID
2168
ICW
West Medicine Hat Lateral 2 (Upstream)
2012 09
2013 11
18%
18%
2 of 11 sites installed
SMRID
2212
ICW
Cameron Lateral
Phase 1
2013 02
2013 10
24%
24%
8710
SMRID
2269
ICW
Aquatic Weed and Algae Control Structures 2014
2013 02
2013 04
40%
100%
2 of 5 sites installed
SMRID
2270
ICW
West Medicine Hat Lateral 13A & 13D
2013 02
2013 10
100%
100%
9598
SMRID
2271
ICW
Chin Lateral 10 Canal Armouring and Structure Replacement
2013 02
2013 09
24%
24%
3365
TID
2267
ICW
Lateral 3
East Horsefly
2013 02
2013 10
75%
75%
5025
TID
2268
ICW
Lateral G
Big Bend
SW 3-11-16-4
2013 09
2014 03
100%
100%
1588
757
UID
2158
ICW
Lateral D-3
& D3a
2009 02
2014 04
95%
100%
3469
UID
2162
ICW
Lateral D-4
2009 02
2013 10
30%
100%
2275
WID
2246
ICW
Secondary A Canal
Rg Rd. 231 to S. Cluny
2013 02
2013 10
100%
100%
3278
TOTALS
6796
54329
15028
GRAND TOTAL
76153
NOTE: * indicates Special Funding used towards this project
 
 
 
 
Share via AddThis.com
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by Bonnie Hofer.
This information published to the web on January 13, 2015.
Last Reviewed/Revised on January 16, 2017.