Taber Irrigation District (TID) - IRP 2014 | |
|
|
|
|
|
|
| During this reporting period the TID expended $2,422,878 of IRP cost shared funds on eleven projects in the ICW and PS categories. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. Those projects with significant construction in 2013/2014 are listed below.
TID IRP Project Construction Summary
August 1, 2013 to July 31, 2014 | Date | % Completed | Rehabilitation Completed
(metres) |
IRP # | ICW/
MW/
PS | Project Name | Project
Approved | Construction
Start | in 13/14 | to July 31/14 | Liners | Pipe | Earth |
2267 | ICW | Lateral 3 East Horsefly | 2013 02 | 2013 10 | 75% | 75% | | 5025 | |
2268 | ICW | Lateral G Big Bend
SW 3-11-16-4 | 2013 09 | 2014 03 | 100% | 100% | | 1588 | 757 |
TOTAL | | 6613 | 757 |
|
|
|
|
|
|