 During this reporting period the SMRID expended $11,871,866 of IRP cost shared funds on eighteen projects in the ICW and PS categories. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. Those projects with significant construction in 2013/2014 are listed below.



SMRID IRP Project Construction Summary
August 1, 2013 to July 31, 2014
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
in 13/14
to July 31/14
Liners
Pipe
Earth
2117
ICW
West Medicine Hat Lateral 16
2010 03
2013 11
100%
100%
5434
2168
ICW
West Medicine Hat Lateral 2 upstream
2012 09
2013 11
18%
18%
2 of 11 drain crossings installed
2212
ICW
Cameron Lateral
2013 02
2013 10
24%
24%
8710
2269
ICW
Aquatic Weed and Algae Control Structures 2014
2013 02
2013 04
40%
100%
2 of 5 sites installed
2270
ICW
West Medicine Hat
Laterals 13A and 13D
2013 02
2013 10
100%
100%
9598
2271
ICW
Chin 10 Canal Armouring
and Structure Replacement
2013 02
2013 09
24%
24%
3365
TOTAL
23742
3365
 
 
 
 
Share via AddThis.com
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by Bonnie Hofer.
This information published to the web on January 13, 2015.