Lethbridge Northern Irrigation District (LNID) - IRP 2014

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 During this reporting period the LNID expended $390,247 of cost shared funds on three projects in the ICW category. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. The LNID did not do any construction under the IRP in 2013/14 in an effort to consolidate funds to complete a larger project in 2014/15.

 
 
 
 