Bow River Irrigation District (BRID) - IRP 2014

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 During this reporting period the BRID expended $4,835,754 of IRP cost shared funds on nine projects in the ICW and PS categories. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. The only project with significant construction in 2013/2014 is listed below.




BRID IRP Project Construction Summary
August 1, 2013 to July 31, 2014
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
in 13/14
to July 31/14
Liners
Pipe
Earth
2259
ICW
Lateral C (West Block)
2013 02
2013 10
100%
100%
16864
TOTAL
16864
 
 
 
 
Share via AddThis.com
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by Bonnie Hofer.
This information published to the web on January 13, 2015.
Last Reviewed/Revised on January 16, 2017.