Taber Irrigation District (TID) - IRP 2013

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 During this reporting period the TID expended $1,368,552 of IRP cost shared funds on twelve projects in the ICW and PS categories. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. Those projects with significant construction in 2012/2013 are listed below.




TID IRP Project Construction Summary
August 1, 2012 to July 31, 2013
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
in 12/13
to July 31/13
Liners
Pipe
Earth
*2217
PS
IDWIMS Redevelopment
2011 02
2011 03
50%
100%
program update
2222
ICW
Lateral K2A Big Bend Pipeline
2011 02
2012 09
100%
100%
987
2261
ICW
North East Big Bend Pipeline
2012 05
2012 11
100%
100%
3795
2265
ICW
Gabion Rock Walls
2013 02
2013 04
100%
100%
2 sites installed
2266
ICW
North Fincastle East Canal (d/s reach)
2013 02
2013 04
100%
100%
400
TOTAL
4782
400
NOTE: * indicates Special Funding used towards this project
 
 
 
 
Share via AddThis.com
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by Bonnie Hofer.
This information published to the web on October 9, 2013.
Last Reviewed/Revised on March 19, 2015.