 During this reporting period the MID expended $44,543 of IRP cost shared funds on three projects in the ICW and PS categories. Some expenditures involved cleanup of previously completed IRP projects and engineering only for future projects. The one project with significant construction in 2012/2013 is listed below.




MID IRP Project Construction Summary
August 1, 2012 to July 31, 2013
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
in 12/13
to July 31/13
Liners
Pipe
Earth
2104
ICW
Highline Canal Seepage Control
2010 02
2012 10
35%
35%
1300 m of drain lines
TOTAL
 
 
 
 
Share via AddThis.com
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by Bonnie Hofer.
This information published to the web on October 9, 2013.
Last Reviewed/Revised on April 16, 2015.