Eastern Irrigation District (EID) - IRP 2013

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 During this reporting period the EID expended $4,713,934 of IRP cost shared funds on seven projects in the ICW and PS categories. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. Those projects with significant construction in 2012/2013 are listed below.




EID IRP Project Construction Summary
August 1, 2012 to July 31, 2013
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
in 12/13
to July 31/13
Liners
Pipe
Earth
*2226
PS
Irrigation Water Quality Assessment
2012 02
2012 06
20%
40%
94 sites sampled
2257
ICW
Secondary B Springhill
2012 02
2012 10
100%
100%
5845
2258
ICW
1064 Check/Chute
2012 02
2013 01
100%
100%
cast-in-place check/drop
TOTAL
5845
NOTE: * indicates Special Funding used towards this project
 
 
 
 
Share via AddThis.com
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by Bonnie Hofer.
This information published to the web on October 9, 2013.
Last Reviewed/Revised on April 16, 2015.