Bow River Irrigation District (BRID) - IRP 2013

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 During this reporting period the BRID expended $3,066,224 of IRP cost shared funds on thirteen projects. MW expenditures total $3,465 and ICW and PS expenditures total $3,062,759. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. Those projects with significant construction in 2012/2013 are listed below.




BRID IRP Project Construction Summary
August 1, 2012 to July 31, 2013
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
in 12/13
to July 31/13
Liners
Pipe
Earth
2214
ICW
Lateral E-2 (Vauxhall Block)
2012 02
2012 10
100%
100%
8119
2235
ICW
Laterals C-8, C-8-3 (Hays Block)
2012 02
2012 09
100%
100%
7028
2241
ICW
Lateral T-1 (Hays Block) Pipeline Extension
2012 02
2012 09
100%
100%
702
2249
ICW
Structure Automation & Flow Measurement 2012
2012 02
2012 04
65%
100%
10 of 16 sites installed
TOTAL
15849
 
 
 
 
Share via AddThis.com
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by Bonnie Hofer.
This information published to the web on October 9, 2013.