Aetna Irrigation District (AID) - IRP 2013

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 During this reporting period the AID expended $18,419 of IRP cost shared funds on three projects in the ICW category. Some expenditures involved cleanup of previously completed IRP projects. One project with significant construction in 2012/2013 is listed below.




AID IRP Project Construction Summary
August 1, 2012 to July 31, 2013
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
in 12/13
to July 31/13
Liners
Pipe
Earth
2275
ICW
Remington Valve Junction
2013 02
2013 05
100%
100%
valve replacements
TOTAL
 
 
 
 
Share via AddThis.com
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by Bonnie Hofer.
This information published to the web on October 9, 2013.
Last Reviewed/Revised on April 16, 2015.