Irrigation Rehabilitation Program Summary of Rehabilitated Lengths to July 31, 2012

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 Table 5 - Irrigation Rehabilitation Program Summary of Rehabilitated Lengths to July 31, 2012
Irrigation District
Total District Systems (km)
Total System Rehabilitated to July 31, 2011 (km)
2011/2012 Rehabilitation (km)
Total to July 31, 2012 (km)
% of Total District System Rehabilitation
Aetna
37.15
22.32
0.35
22.67
61%
Bow River
1005.28
777.84
30.55
808.39
80%
Eastern
1920.38
791.74
15.90
807.64
42%
Leavitt
53.44
40.44
1.07
41.51
78%
Lethbridge Northern
744.30
542.31
0
542.31
73%
Magrath
100.60
88.45
0
88.45
88%
Mountain View
39.66
33.73
0
33.73
85%
Raymond
230.21
211.35
4.10
215.45
93%
Ross Creek
26.34
21.69
0
21.69
82%
St. Mary River
1823.66
1204.30
23.33
1227.63
67%
Taber
337.59
309.48
5.90
315.38
93%
United
236.77
152.01
3.49
155.50
66%
Western
1064.52
321.46
20.56
342.02
30%
TOTALS
7619.90
4517.12
105.25
4517.12
61%

Note:
  1. Lengths in AID, BRID, EID, LNID, SMRID, UID, & WID exclude Main Canals that were rehabilitated under Alberta Environment's Water Management Systems Improvement Program.
  2. Total Systems Rehabilitated for EID does not include Bank Rebuilding Projects constructed from 1977 to 1982.
  3. Total Systems Rehabilitated for WID does not include "TREE REMOVAL" Projects.
  4. Totals do not include drainage works.
  5. Totals do not include works rehabilitated by a district using its own funds.
  6. Total length differs from Table 4 due to recurrent rehabilitation.
  7. Total Systems Rehabilitated under the IRP to July 31, 2011 is based on the Water Resources Branch current 2012 IIMS database.
 
 
 
 
Share via AddThis.com
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by Bonnie Hofer.
This information published to the web on December 11, 2012.