Taber Irrigation District (TID) - IRP 2012

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 During this reporting period the TID expended $1,328,045 of IRP cost shared funds on twelve projects. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. Those projects with significant construction in 2011/2012 are listed below.



TID IRP Project Construction Summary
August 1, 2011 to July 31, 2012
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
in 11/12
to July 31/12
Liners
Pipe
Earth
2220
ICW
Lateral J Big Bend Pipeline
2011 02
2011 11
100%
100%
260
2223
ICW
Lateral N1 Big Bend Pipeline
2011 02
2011 10
100%
100%
3630
2242
ICW
Lateral E Cranford (d/s reach)
2012 02
2012 03
100%
100%
2013
TOTAL
5903
 
 
 
 
Share via AddThis.com
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by Bonnie Hofer.
This information published to the web on December 11, 2012.