 During this reporting period the RCID expended $12,000 of IRP cost shared funds on one project in the ICW category. This project is listed below.



RCID IRP Project Construction Summary
August 1, 2011 to July 31, 2012
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
in 11/12
to July 31/12
Liners
Pipe
Earth
2148
ICW
Ross Creek Diversion Canal
2012 02
2011 05
100%
100%
Replace washed out field crossing
TOTAL
 
 
 
 