 During this reporting period the BRID expended $7,903,246 of IRP cost shared funds on sixteen projects. MW expenditures total $9,730 and ICW and PS expenditures total $7,893,516. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. Those projects with significant construction in 2011/2012 are listed below.



BRID IRP Project Construction Summary
August 1, 2011 to July 31, 2012
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
in 10/11
to July 31/11
Liners
Pipe
Earth
2186
ICW
Lateral H-2-2 (West Block)
2010 02
2011 11
100%
100%
2948
2195
ICW
Lateral A-2 (West Block)
2011 08
2011 10
100%
100%
1800 (drain)
2206
ICW
Lateral B-4 (West Block) Pipeline Extension
2011 02
2011 10
100%
100%
2177
2207
ICW
Laterals J & J-1 (Vauxhall Block)
2011 02
2011 09
100%
100%
25424
2249
ICW
Structure Automation & Flow Measurement 2012
2012 02
2012 04
35%
35%
6 of 16 sites installed
TOTAL
30549
1800
 
 
 
 
Share via AddThis.com
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by Bonnie Hofer.
This information published to the web on December 11, 2012.
Last Reviewed/Revised on December 13, 2016.