St. Mary River Irrigation District (SMRID) - IRP 2011

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 During this reporting period the SMRID expended $9,142,581 of IRP cost shared funds on twenty-eight projects. MW expenditures total $448,397 and ICW & PS expenditures total $8,694,184. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. Those projects with significant construction in 2010/2011 are listed below.



SMRID IRP Project Construction Summary
August 1, 2010 to July 31, 2011
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
in 10/11
to July 31/11
Liners
Pipe
Earth
1799
ICM
Bow Island Lateral 26 Concrete
1998 06
2008 10
25%
57%
8898
1862
ICM
North Lateral Gravel Armouring
2001 12
2002 10
21%
100%
1112
2314
2052
ICM
Yellow Lake Lateral 4
2006 02
2007 10
29%
100%
5531
2153
ICM
Chin Lateral 11
2010 02
2011 01
100%
100%
1475
2168
ICM
West Medicine Hat Lateral 2 (upstream)
2009 02
2010 11
37%
37%
7257
2188
ICM
Bow Island Lateral 10D
2010 02
2010 10
100%
100%
4989
2192
ICM
SMRID Aquatic Weed and Algae Control Project (2010)
2009 11
2010 01
40%
100%
install 2 weed control sites
2201
ICM
Aquatic Weed and Algae control structures (2011)
2010 02
2011 01
100%
100%
install 9 weed control sites
2208
ICM
SCADA Infrastructure Upgrade (SMRID East)
2010 04
2010 05
100%
100%
upgrade SMRID East SCADA
2213
MW
Northeast Lateral Section 15-10-20-W4
2010 09
2010 10
100%
100%
1873
TOTAL
1112
28150
4187
 
 
 
 
Share via AddThis.com
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by Bonnie Hofer.
This information published to the web on January 25, 2012.
Last Reviewed/Revised on August 30, 2017.