United Irrigation District (UID) - IRP 2010 | |
|
|
|
|
|
|
| During this reporting period the UID expended $981,272 of IRP cost shared funds on ten projects in the ICW category. Some expenditures involved cleanup of previously completed IRP projects or engineering only for upcoming projects. Those projects with significant construction in 2009/2010 are listed below.
UID IRP Project Construction Summary
August 1, 2009 to July 31, 2010 | Date | % Completed | Rehabilitation Completed
(metres) |
IRP # | ICW/
MW/
PS | Project Name | Project
Approved | Construction
Start | in 09/10 | to July 31/10 | Liners | Pipe | Earth |
2092 | ICW | Lateral A1C | 2007 02 | 2009 08 | 100% | 100% | | 2671 | |
2130 | ICW | UID Inflow Metering Stations | 2008 02 | 2010 06 | 50% | 100% | 2 flow meters installed |
2159 | ICW | Lateral B4 | 2009 02 | 2009 11 | 100% | 100% | | 1673 | |
2161 | ICW | Lateral D | 2009 02 | 2010 03 | 17% | 17% | | | 851 |
2163 | ICW | Lateral Da | 2009 02 | 2010 05 | 100% | 100% | | 1356 | |
TOTAL | | 5700 | 851 |
|
|
|
|
|
|
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by .
This information published to the web on January 17, 2011.
Last Reviewed/Revised on December 6, 2017.
|
|