Irrigation Rehabilitation Program Project Construction August 1, 2015 to July 31, 2016

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 Table 2 - Project Construction

Rehabilitation Completed
(lengths in metres)
Irrigation Distrct
Project #
ICW
MW
PS
Project Name
Project Approval Date
Construction Start Date
% Completed in 15/16
% Completed to July 31/16
Liners
Pipe
Earth
BRID
2297
ICW
Lateral C-7
2015 02
2015 09
95
100
4,220
BRID
2299
ICW
Lateral H-6-3,K-11-A, C,D,E
2015 02
2015 10
95
100
15,154
EID
2314
ICW
01 Bow Slope
2015 02
2015 11
99
100
20,850
LID
2316
ICW
Lateral D Screen Upgrades
2016 04
2016 04
100
100
LNID
2202
ICW
Laterals H3/H8
2011 02
2014 05
20
100
6,270
MID
2104
ICW
High Line Seepage Control
2010 02
2014 11
38
100
467 m (drain tile)
RID
2307
ICW
Welling Lateral #5
2015 02
2015 11
99
100
2,661
SMRID
1799
ICW
Bow Island Lateral 26
1998 06
2015 10
7
80
5,379
SMRID
2198
ICW
South Grassy Main
2010 02
2016 01
11
11
24
SMRID
2271
ICW
Chin Lateral 10
2013 06
2015 10
34
58
650
3,038
SMRID
2311
ICW
Aquatic Weed and Algal Control Structures
2015 06
2016 03
100
100
4 sites
TID
2303
ICW
Lateral 18 Taber
2014 10
2015 09
89
100
7,009
TID
2313
ICW
Aquatic Weed and Algal Control Structures 2016
2015 02
2015 10
85
100
4 gabion walls and 2 mechanical screen cleaners
UID
2263
ICW
Lateral E
2013 02
2013 03
43
100
1,206
UID
2300
ICW
Lateral A1d
2015 02
2016 04
100
100
537
WID
2304
ICW
Standard Lateral 85N7, 85N8, 85N9
2015 04
2015 10
100
100
13,627
TOTALS
650
76,937
3,038
GRAND TOTAL
80,625 metres

 
 
 
 
Share via AddThis.com
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by Bonnie Hofer.
This information published to the web on March 24, 2017.