Western Irrigation District (WID) - IRP 2016

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 During this reporting period the WID expended $4,504,100 of IRP cost shared funds on six projects in the ICW category. Expenditures involved cleanup of previously completed IRP projects or engineering for upcoming projects.

WID IRP Project Construction Summary
August 1, 2015 to July 31, 2016
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
in 15/16
to July 31/16
Liners
Pipe
Earth
2108
ICW
Sublateral 74T4 & 84T4A
(Cemetery Hill)
2014 01
2014 09
<1
100
2278
ICW
A Canal
Sublateral 81F11
2014 01
2014 10
<1
100
2279
ICW
North Cluny
Lateral 83H6
2014 01
2015 01
2
100
2304
ICW
Standard Lateral
85N7, 85N8, 85N9
2015 04
2015 10
100
100
13,627
2305
ICW
Standard Lateral
85N6
2016 02
N/A
6
6
13,627
 
 
 
 