United Irrigation District (UID) - IRP 2016

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 During this reporting period the UID expended $467,362 of IRP cost shared funds on four projects in the ICW category. Expenditures involved cleanup of previously completed IRP projects, pipeline installation and preliminary work for upcoming projects.



UID IRP Project Construction Summary
August 1, 2015 to July 31, 2016
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
in 15/16
to July 31/16
Liners
Pipe
Earth
2263
ICW
Lateral E
2013 02
2015 03
43
100
1,206
2300
ICW
Lateral A1d
2015 02
2016 04
100
100
537
2301
ICW
Lateral A1
2016 02
N/A
2
2
2320
ICW
Lateral A4.5
2016 04
N/A
10
10
1,743
 
 
 
 