Lethbridge Northern Irrigation District (LNID) - IRP 2016

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 During this reporting period the LNID expended $3,916,545 of cost shared funds on two projects in the ICW category, which involved the installation of a pipeline and preliminary work.



LNID IRP Project Construction Summary
August 1, 2015 to July 31, 2016
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
in 15/16
to July 31/16
Liners
Pipe
Earth
2202
ICW
Laterals H3/H8
2011 02
2014 05
20
100
6,270
2302
ICW
Laterals H9
2015 02
N/A
4
4
6,270
 
 
 
 