Bow River Irrigation District (BRID) - IRP 2016

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 During this reporting period the BRID expended $3,823,227 of IRP cost shared funds on eight projects in the ICW and PS categories. Expenditures involved pipeline installation, cleanup of previously completed IRP projects or engineering for upcoming projects.



BRID IRP Project Construction Summary
August 1, 2015 to July 31, 2016
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
in 15/16
to July 31/16
Liners
Pipe
Earth
*2227
PS
Irrigation Demand Model (IDM)
2011 02
N/A
35
100
2236
ICW
Lateral M1 (Hays Block)
2014 01
2014 10
4
100
2264
ICW
Lateral D-4 (West Block)
2014 01
2014 10
0
100
2297
ICW
Lateral C-7 (Hays Block)
2015 02
2015 09
95
100
4,220
2299
ICW
Lateral H-6-3, K-11-A, K-11-C,
K-11-D, K-11-E (Vauxhall Block)
2015 02
2015 10
95
100
15,154
2309
PS
Badger Reservoir
Dam Safety Review
2015 02
N/A
100
100
2317
PS
Aerial Photography 2015
2015 04
N/A
100
100
2319
ICW
Lateral B (West Block)
2016 02
2016 04
10
10
19,374
NOTE: * indicates Special Funding used towards this project. The funding was allocated to BRID in 2011/12
 
 
 
 
Share via AddThis.com
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by Bonnie Hofer.
This information published to the web on March 20, 2017.