Irrigation Rehabilitation Program Summary of Rehabilitated Lengths to July 31, 2015

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 Table 4 - Irrigation Rehabilitation Program Summary of Rehabilitated Lengths to July 31, 2015
Irrigation District
Total District Systems (km)
Total System Rehabilitated to July 31, 2014 (km)
2014/2015 Rehabilitation (km)
Total to July 31, 2015 (km)
% of Total District System Rehabilitation
Aetna
37.89
22.99
0.00
22.99
61%
Bow River
999.30
811.00
13.29
824.29
82%
Eastern
1911.71
798.54
26.58
825.12
43%
Leavitt
54.75
41.34
0.00
41.34
76%
Lethbridge Northern
751.17
559.42
16.28
575.70
77%
Magrath
100.81
90.67
0.00
90.67
90%
Mountain View
39.67
33.83
1.98
35.81
90%
Raymond
236.39
215.94
2.20
218.14
92%
Ross Creek
12.18
12.18
0.00
12.18
100%
St. Mary River
1804.64
1250.95
7.22
1258.17
70%
Taber
342.74
324.76
0.00
324.76
95%
United
233.08
160.61
4.40
165.01
71%
Western
1062.22
339.69
11.38
351.07
33%
TOTALS
7586.55
4661.92
83.33
4745.25
62%

Note:
  1. Lengths in AID, BRID, EID, LNID, SMRID, UID, & WID exclude Main Canals that were rehabilitated under Alberta Environment's Water Management Systems Improvement Program.
  2. Total Systems Rehabilitated for EID does not include Bank Rebuilding Projects constructed from 1977 to 1982.
  3. Total Systems Rehabilitated for WID does not include "Tree Removal" Projects.
  4. Totals do not include drainage works.
  5. Totals do not include works rehabilitated by a district using its own funds.
  6. Total length differs from Table 4 (Totals) due to recurrent rehabilitation.
  7. Total Systems Rehabilitated under the IRP to July 31, 2014, and Total District Systems are based on the Basin Water Management Branch current 2015 IIMS database.
 
 
 
 