Western Irrigation District (WID) - IRP 2015

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 During this reporting period the WID expended $2,455,218 of IRP cost shared funds on five projects in the ICW category. Expenditures involved cleanup of previously completed IRP projects, installation of pipeline and preliminary work on upcoming projects.




WID IRP Project Construction Summary
August 1, 2014 to July 31, 2015
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
in 14/15
to July 31/15
Liners
Pipe
Earth
2108
ICW
Sublateral 74T4 & 84T4A
(Cemetery Hill)
2014 01
2014 09
100
100
3,138
2246
ICW
Secondary A Canal
Rg Rd 231 to S. Cluny
2013 02
N/A
3
100
2278
ICW
A Canal
Sublateral 81F11
2014 01
2014 10
100
100
4,203
2279
ICW
North Cluny
Lateral 83H6
2014 01
2015 01
87
94
4,036
2304
ICW
Standard Lateral
85N7, 85N8, 85N9
2015 04
N/A
3
3
11,377
 
 
 
 
Share via AddThis.com