 During this reporting period the TID expended $1,283,163 of IRP cost shared funds on eleven projects in the ICW category. Expenditures involved cleanup of previously completed IRP projects, installation of canal liner, plastic drain tile, gabion walls and screen cleaners and preliminary work on upcoming projects.




TID IRP Project Construction Summary
August 1, 2014 to July 31, 2015
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
in 14/15
to July 31/15
Liners
Pipe
Earth
1988
ICW
Big Bend Main Canal
2004 02
2014 11
66
100
590
2239
ICW
Lateral E-3 Big Bend
Pipeline
2012 03
N/A
<1
100
2266
ICW
North Fincastle East Canal
d/s Reach
2013 02
N/A
<1
100
2267
ICW
Lateral 3
East Horsefly
2013 02
2014 10
25
100
1700 m plastic drain tile
2268
ICW
Lateral G Big Bend
SW 3-11-16-W4
2013 09
N/A
<1
100
2282
ICW
Long Term
Infrastructure Plan
2014 01
2014 05
100
100
2283
ICW
Aquatic Weed & Algae
Control Structures (2015)
2014 01
2015 02
100
100
7 gabion walls and 2 automated
mechanical screen cleaners
2285
ICW
Overshot Control Gate
Taber Main Canal at Lateral 11
2014 01
N/A
62
62
2286
ICW
Overshot Control Gate
East Horsefly Main Canal at Lateral 10
2014 01
N/A
73
73
2303
ICW
Lateral 18 Taber
2014 10
N/A
0
0
2313
ICW
Aquatic Weed and Algae Control
Structures (2016)
2015 02
N/A
0
0
 
 
 
 
Share via AddThis.com
For more information about the content of this document, contact Rebecca Fast.
This document is maintained by Bonnie Hofer.
This information published to the web on June 1, 2016.