St. Mary River Irrigation District (SMRID) - IRP 2015

 
 
Subscribe to our free E-Newsletter, "Agri-News" (formerly RTW This Week)Agri-News
This Week
 
 
 
 During this reporting period the SMRID expended $4,886,896 of IRP cost shared funds on sixteen projects in the ICW and PS categories. Expenditures included cleanup of previously completed IRP projects, installation of pipelines, gabion walls and screen cleaners and preliminary work on new projects.



SMRID IRP Project Construction Summary
August 1, 2014 to July 31, 2015
Date
% Completed
Rehabilitation Completed
(metres)
IRP #
ICW/
MW/
PS
Project Name
Project
Approved
Construction
Start
in 14/15
to July 31/15
Liners
Pipe
Earth
1799
ICW
Bow Island Lateral 26
Concrete
1998 06
2014 10
11
84
2117
ICW
West Medicine Hat Lateral 16
2010 03
N/A
2
100
2168
ICW
West Medicine Hat
Lateral 2 (upstream)
2009 02
2014 11
2
100
2176
ICW
Yellow Lake Lateral 13
2010 02
N/A
<1
100
2198
ICW
South Grassy Main
2010 02
N/A
1
1
2212
ICW
Cameron Lateral
2011 02
N/A
<1
24
2250
PS
Water Storage
Opportunities - Study
2012 02
N/A
14
100
2251
ICW
Yellow Lake Lateral 11
2012 02
N/A
<1
100
2253
ICW
Coaldale Lateral
2015 02
2015 03
29
29
1,092
2269
ICW
Aquatic Weed and Algae Control
Structures 2014
2013 02
N/A
1
100
2270
ICW
West Medicine Hat Lateral
13A and 13D
2013 02
N/A
3
100
2271
ICW
Chin Lateral 10 Canal Armouring
and Structure Replacement
2013 02
N/A
4
27
2273
PS
NE Reservoir Dam Safety
Review
2013 02
N/A
3
22
2288
ICW
Bow Island Lateral 7
Pipeline
2014 01
2014 10
100
100
2,221
2289
ICW
Aquatic Weed and Algae Control
Structures 2015
2014 01
N/A
90
100
5 sites installed
2290
PS
Dam Safety Review for Stafford,
Grassy Lake, and Lateral 10 Reservoirs
2014 01
N/A
78
78
7,220
 
 
 
 